Vannessa Ventures Crucitas
Project Update
Vannessa Ventures Ltd. through
its 100 percent owned
subsidiary, Industrias Infinito
S.A., has now supplied the
Ministry of Environment in Costa
Rica (SETENA) with all of the
information requested to enable
SETENA to issue a final
resolution and specify the
details of the required
Environmental Performance Bond
for its Las Crucitas Project.
Vannessa's submission included
confirmation of specific
commitments previously made by
the Company and updated
estimates of project initial
capital costs.
Vanessa is moving forward with
the development of the project
and is in the process of
engaging geological consultants
to complete a resource estimate
of the entire deposit compliant
with National Instrument 43-101.
In addition, Vanessa is in
discussions with various
consultants in the fields of
mineral processing,
infrastructure construction and
other relevant areas in order to
complete a bankable feasibility
study on the project building on
the extensive work already
carried out on the property.
Vanessa has retained the
services of Dr. John Thomas, a
qualified metallurgist with a
broad base of international
experience in constructing and
operating gold mines. Most
recently Dr. Thomas was
responsible for constructing and
commissioning the Choco 10 mine
in Venezuela for Bolivar Gold
Corp. Dr. Thomas also serves as
a Director of the Company.
The Crucitas gold deposit, which
lies in Alejuela Province, in
North Central Costa Rica, has
undergone extensive exploration
work in the period 1992-1998
when the property was held by a
subsidiary of Placer Dome Inc. A
total of 251 diamond drill
holes, 27 geotechnical and
hydro-geological holes, and 90
Trado (auger) holes were
completed over the property
comprising more than 36,000
meters of total drilling and
over 32,000 gold and silver
assays were taken. Lyon Lake
Mines Ltd., who acquired the
property in 1998, hired Cambior
Project & Construction Group (Cambior)
to coordinate a feasibility
study in 1999. Cambior engaged
Independent Mining Consultants,
Inc. (IMC) to complete the
Reserve and Resource estimates
and the Mine Plan. IMC completed
a review of the Placer Dome Inc.
exploration program and results
including sampling split core
which is still in place on the
project site.
|
|