San Sebastian Rotonda To Have An
Overpass
In the coming weeks construction
is to begin on the overpass at
the San Sebastián rotonda, one
of the busiest round abouts on
the Circunvalación - rind road -
on the south side of San José.
The rotonda sees some 50.000
vehicles a day as five
intersections meet, from those
travelling to and from downtown
San José, across the city in an
east-west direction and to and
from the Hipermas shopping
centre and other retail
locations located along the side
of the Circunvalación.
The plan for the construction of
an overpass similar to that at
the Desamparados/Dos Rios
rotonda were announced last year
and the trees and other material
from the centre of the rotonda
were cleared long ago as work
then came to a sudden hault.
However, Pedro Castro,
vice-minister of Obras Pública
(Public Workds) said yesterday
that the "five year old" project
will soon be brough back to
life.
One of the systems considered by
the Ministerio de Obras Pública
y Transportes (MOPT) - public
works and transportation
minister - was to signalize the
intersection, which would have
cost much less than building an
overpass. However, traffic
studies indicate that the
signalization the intersection
with traffic lights would not be
a solution to moving traffic
throuhg the busy intersection.
MOPT officials are looking to
begin construction of the
overpass before the end of this
year, which will see a overpass
move traffic in the east-west
direction and an underpass move
traffic in the north-south
direction, with exits to the
local side streets.
The cost of the project has been
doubled because of the delays.
The cost of erecting traffic
lights at the intersection would
set back the MOPT an estimated
us$1 million dollars, while the
cost of constructing an overpass
is estimated at us$3.5 million
dollars. However, like many
public projects in Costa Rica,
that final bill for the
construction could be as much as
double that.
Castro added that one of the
major reasons for the delay was
to appease residents of the area
who became concerned on how
pedestrians would cross the
intersection. A pedestrian
bridge will also be built to
accommodate the concern.
However, before that can happen,
the Contraloría General de la
República (Comptroller's office)
has to approve the pedestrian
bridge contract and allow both
contractors to work at the same
time on the intersection.
The overpass contract was
awarded to the firm Sánchez
Carvajal with a time frame of
nine months from start to
finish.
The other intersections on the
Circunvalación to continue with
rotondas is the Alajuelita, Paso
Ancho and Zapote. All other
intersections on the
Circunvalación, save the
Desamparados/Dos Rio, which
continues with a rotonda under
the overpass, have traffic
lights.
|
|

An overpass similar to the one
at the Desamparados/Dos Rios
rotonda (pictured above) will be
built at the busy intersection
of San Sebastian on the
Circunvalación.
The intersection sees some
50.000 cars daily that move in
five directions. |
|
|
|
|
|