June 8th, 2015 (InsideCostaRica.com) The Costa Rican Institute of Aqueducts and Sewers (AyA) is in the final stages of securing $130 million in financing in order to repair leaks in its distribution network. More than 600 kilometers of aqueducts would be completely replaced, while nearly 5,000 kilometers will be inspected and repaired.
The Institute currently loses some 50% of all the water it distributes, mostly due to leaks in piping, aqueducts and water mains.
The Central American Bank for Economic Integration (BCIE) and Germany’s KfW Development Bank will together provide $130 million in financing. Work could begin next year and be completed by 2022, La Nacion reports.
The work will be carried out on the water systems in the greater San Jose metro area, as well as Limón, Guácimo, San Isidro de Pérez Zeledón, El Pasito de Alajuela, San Ramón, Puntarenas, Liberia and Nicoya.