Bridge Inspection Contract Had Been Cancelled Due To Lack of Funds

Another contributing factor can be added to the fatal accident last Thursday at the Turrubares bridge, lack of money on the part of the Ministerio de Obras Públicas y Transportes (MOPT) to keep the bridges around the country safe, this admitted yesterday by former MOPT minister, Karla González and the director of the Consejo Nacional de Vialidad (Conavi), Alejandro Molina.

The MOPT, at the beginning of the hired, unveiled new inspectors that would be responsible to keep an eye of the more than 1.300 bridges across the country.

Thier job was to check of cracks in the pavement, damage to tension cables, railings and signage, among other items. These continuous checks would ensure that bridges deemed unsafe would be closed to vehicular traffic and wait repair.

However, as the former minister and Conavi director admitted, there was no money by September to continue the work of the inspectors.

The inspectors were not employees of the MOPT, but rather contracted employees under contract with private companies dedicated to road inspection and safety, costing the government us$4.200 for each inspector.

For lack of funds, the contracts were cancelled and the bridges were ignored. Conavi was the responsible government agency to pay the inspectors, which in September did not have the money to pay the salaries, according to Molina, who added that the funds that were to used for the inspectors, went to pay for emergencies like the earthquake in Cinchona (January 8).

The lack of financings had a direct impact on the cancelling of the inspections.

Former minister González said the hiring of the inspectors was instituted after a report by the Agencia de Cooperación Japonesa (JICA) revealed that a large number of the bridges in the country were in a bad state of repair.

The former minister said that the inspection had been the first initiative in the last 40 years.

Benjamín Sandino, director de Conservación Vial del Conavi, said that the inspectors filled out a form of the basic condition of the bridge, the information the used by the supervisor to determine what repair or maintenance work was required.

Molina added that after the inspector contract was cancelled, engineers contracted to inspect roads were also asked to inspect bridges. As of this week, a number of Tránsito officials (traffic police officials) have been given orders to inspect a number of bridges.

Molina said that beginning in 2010, the Conavi will have 42 new people dedicated exclusively to the design, construction and maintenance of bridges.
 








 
 

 

 


 
 
 
 