San José - Caldera Highway Gets Green Light For Completion

The Tribunal Ambiental Administrativo gave the Autopistas de Sol the green light yesterday to continue work on the San José - Caldera highway.

Work on the section between Santa Ana and Orotina of the highway, which links San José to the port town of Caldera, Puntarenas, was stopped last month after environmental concerns, specifically in the area known as Barva, were denounced against the contractor.

Environmental officials have been investigating the complaints since as the highway work affects some 20 rivers and creeks and has local residents up in arms.

The Tribunal, although it will allow the workd to continue, will ensure that environmental officials keep a close eye on the situation.

The San José - Caldera highway has been in the planning and construction stage for almost 30 years. It wasn't until two years ago that the Autopistas del Sol, a Spanish consortium,  was given the concession to complete the construction of the highway and charge tolls to recover its investment.

The section between San José (the east end of the Sabana park) and Piedades de Santa Ana (although it is referred to as Cuidad Colón) and the section between Orotina and Caldera have been completed.

What remains is the middle section that should be completed by mid 2010.

 
 











 
 

 

 


 
 
 
 