General Cañas Reopens Following Weekend Closure

It was shortly after 4am this morning, Monday, that work crews removed the last barrier that shut down completely the westbound lanes of the autopista Genaral Cañas at the virilla bridge, that had been closed since Saturday morning.

The Consejo Nacional de Vialidad (Conavi) workers are confident that the weekend work on the bridge will take this time and not breakdown like the work performed on the bridge two weekends ago, that also required a complete shut down of the highway, last less than 48 hours.

This time workers replaced the metal plate which had been used to patch up the bridge for almost a year, with a concrete expansion joing.

Benjamín Sandino, head of the Conavi, explained that the repair has to allow for the natural movement of the bridge and a special joint compound was used during this repair effort.

Meanwhile, traffic congestion from San José to Alajuela was not that bad this time around, as many decided to stay home this weekend and not travel west from San José, although traffic around La Uruca and the Juan Pablo II bridge was heavier than most weekdays.

Two weekends ago traffic congestion in La Uruca and Santa Ana, the two alternate routes, created a traffic nightmare as it took up to three hours to move from La Sabana to the airport, a trip that takes not more than 15 minutes during normal traffic.
 




 
 
 


 

 