Road to Caldera and Costanera Sur To be Completed Ahead of Schedule

Guillermo Matamoros, viceministro de Concesiones for the MOPT, the new road to Caldera and the last 40 kilometres of the Costanera Sur, said on Friday that the two roads should be ready earlier than expected, in the first months of 2010, as the projects are about 90% complete.

According to Hadda Muñoz, manager of the new road to Caldera, said that only 3.6 kilometres or the 77 kilometres are left unfinished in the San José - Caldera highway, and if the work continues at the same pace, the road should be ready ahead of anticipation.

Both Muños and Matamoros assure that the new road will be operation by March 2010 and not July 2010 as had been scheduled. The only roadblock that could prevent the early opening is complications in environmental issues that have plagued the road building between Santa Ana and Orotina.

As to the Costanera Sur, Carlos Acosta, engineer for the project said that the road is 95% complete and that only 4 kilometres of the 42 have to be asphalted.

Acosta said that the setback on the last four kilometres was a problem with expropriations, but that has been resolved and the work can no be completed.

Once completed, the Costanera Sur will connect the Pacific port town of Quepos with Dominical.

 
 
 
 

 

 


 
 
 
 