|
Alterra Expects Renewal of
Airport Contract
Airport concessionaire Alterra
Partners expects approval from
the Costa Rican government for
the International Finance
Corporation's (IFC) proposal to
renew its us$172 million dollar
concession to complete the Juan
Santamaría (San José)
international airport, Alterra
executive director Mónica Nagel
said.
The initial proposal from the
World Bank (WB), through its
private sector arm, the IFC, and
10 other creditors, was
submitted on December 22, 2006.
Now, the creditors are "working
to develop this proposal, and
Alterra is cooperating with them
so it can be presented as soon
as possible," said Nagel. "We
expect the government of Costa
Rica to take this opportunity
that the WB is giving it to
continue with construction works
at the airport."
The creditors submitted the
proposal with additional support
from the Central American Bank
for Economic Integration (Cabei),
which pledged us$48 million to
the project, with an additional
us$4 million coming from
independent investors,
BNamericas reported previously.
The total us$52 million would
cover the remaining costs of
Alterra Partners' works at the
airport.
The proposal came in response to
an ultimatum from the transport
ministry giving the creditors 30
days to submit a plan to finance
the remainder of the project, or
have the rights for the works
revoked within seven months.
The ultimatum was made following
a 2003 decision by creditors to
stall funding for the project
due to a disagreement over a
clause stipulating how much
Alterra could charge in tariffs
at the airport.
As a result, Alterra claimed it
had lost us$18.7 million in
revenue, raising doubts over
whether the concessionaire could
come up with the necessary funds
to pay back its loans.
But while negotiations continue
over the financial structure,
"works [at Santamaría] have been
advancing," Nagel said. However,
the executive director added
that progress is "not at the
rhythm [it] should be due to the
lack of finance from the IFC in
response to the change in
tariffs from the government of
Costa Rica in 2003."
As a result, the government will
need to extend the concession
contract by five years, pushing
back the final completion date
to 2026, from the 2021 deadline
stipulated in the original
contract, said Nagel.
Phases one and two of the works
are due to be completed by the
end of 2008, and phases three
and four by 2021, said the
director.
The December 22 proposal also
includes a restructuring of the
financing scheme for the
project. The IFC agreed to
extend Alterra's deadline for
paying back the loan by seven
years to 2022.
To date, us$120 million has been
invested in the project, us$90
million from the banks and us$30
million from independent
investors.
|
|